Installation of new glycol cooling pipework for 2 off additional Maturation Vessels at a brewery packaging plant in Bridgwater.
All wiring and control modifications to integrate the new vessels into the existing control system installed by CSPS 3 years earlier.
Working with the customer to commission the new vessels and set up purge and prime interfaces used in the production process.